N19 Shannon Airport Access Road
Improvement Scheme

Dept. Transport Standard 1.0

NewsUpdates

Update No. 13: November 2022 - EIAR Scoping Report

By: Shannon Access
Posted on: 03-Nov-2022
Clare County Council intends to submit a planning application to An Bord Pleanála for the Project accompanied by an Environmental Impact Assessment Report (EIAR). As part of the preparation of the EIAR, Clare County Council has prepared a Scoping Report. It is available to view under Consultations.  All consultation received as part of this scoping process will be considered in the preparation of the EIAR to accompany the planning application.   

Read more


Update No. 12: February 2022 - Phase 3 (Design and Environmental Evaluation) Commences

By: Shannon Access
Posted on: 21-Feb-2022
Phase 2 (Options Selection) concluded in January 2022 following Public Display of the Preferred Option which took place between 22nd November 2021 and 6th December 2021. Following this Public Display the Option Selection Report was finalised which presents the outcome of the option selection process and identifies the Preferred Option to be taken forward to the next stages of the scheme development. Details of the preferred option are available here.

Read more


Update No. 10: 22 November 2021 - Public Display of the Preferred Option

By: Shannon Access
Posted on: 22-Nov-2021
Public Display of the Preferred Option is now live until 6th December 2021.

Read more


Update No. 9: 16 November 2021 - Upcoming Public Display of the Preferred Option

By: Shannon Access
Posted on: 16-Nov-2021
Public Display of the Preferred Option will commence on 22nd November 2021 at 3pm.

Read more


Update No. 7: Appropriate Assessment (AA) for Screening for Ground Investigations

By: Shannon Access
Posted on: 01-Apr-2021
Clare County Council has carried out an Appropriate Assessment (AA) Screening Report and has determined that a full Appropriate Assessment is not required in respect of the proposed N19 Shannon Airport Access Road Improvement Scheme Ground Investigations. A copy of the Appropriate Assessment (AA) Screening Report is available for download here.

Read more


Update No. 6: (March 2021) – Phase 2 Options Selection Progress

By: Shannon Access
Posted on: 04-Mar-2021
Introduction Clare County Council, in partnership with Transport Infrastructure Ireland (TII), is developing the planning and design for the N19 Shannon Airport Access Road Improvement Scheme. 

Read more


Update No. 5 (Public Consultation No.1 - Now Closed)

By: Shannon Access
Posted on: 03-Dec-2020
Public Consultation No. 1 – ‘Constraints & Preliminary Route Options’ ran from 12 November 2020 to 02 December 2020 and is now closed.

Read more


Update No. 4 (Public Consultation No. 1 – November 2020) – Constraints & Preliminary Route Options

By: Shannon Access
Posted on: 12-Nov-2020
Public Consultation No. 1 – Constraints & Preliminary Route Options, is now live. Please click here to view the consultation information.

Read more